5 | Before fabrication or procurement | |||||||||
M3 | Grooved end couplings | 9.1.1 9.2.1 9.3.1 | 86-68420 | (1) Commercial products data (2) Details of pipe ends | 0 | 3 | 5 | Before fabrication or procurement | ||
M4 | Pressure gauges | 9.1.1 9.2.1 9.2.2 9.3.1 | 86-68420 | Commercial products data | 0 | 3 | 5 | Before fabrication or procurement | ||
M5 | Hydraulic dampened check valves | 9.1.1 9.2.1 | 86-68420 | Commercial products data | 0 | 3 | 5 | Before fabrication or procurement | ||
M6 | Manually operated butterfly valves | 9.1.1 9.2.1 9.2.2 9.3.1 | 86-68420 | Commercial products data | 0 | 3 | 5 | Before fabrication or procurement | ||
M7 | Motor operated butterfly valves | 9.1.1 9.3.1 | 86-68420 | (1) Commercial products data (2) Test data (3) Torque calculations (4) Assembly drawings (5) Schematic and wiring diagrams | 0 | 3 | 5 | Before fabrication or procurement | ||
M8 | Pressure-sustaining and check valves | 9.1.1 9.3.1 | 86-68420 | Commercial products data | 0 | 3 | 5 | Before fabrication or procurement | ||
M9 | Ball valves | 9.1.1 9.2.1 9.3.1 | 86-68420 | Commercial products data | 0 | 3 | 5 | Before fabrication or procurement | ||
M10 | Air valves | 9.1.1 9.2.1 9.3.1 | 86-68420 | Commercial products data | 0 | 3 | 5 | Before fabrication or procurement | ||
M11 | Elevated steel tanks | 9.1.1 9.2.2 | 86-68420 | (1) Shop drawings (2) Design calculations (3) Erection engineer qualifications | 0 | 3 | 5 | Before fabrication or procurement | ||
M12 | Safety rail | 9.1.1 9.2.2 | 86-68420 | Commercial products data | 0 | 3 | 5 | Before fabrication or procurement | ||
M13 | Metal piping for sectionalizing valve and farm unit irrigation installations | 9.1.1 9.3.1 | 86-68420 | Shop drawings for information only | 0 | 3 | 1 | Before fabrication or procurement | ||
M14 | Combination rate of of flow controller, pressure reducing, and pressure staining valves | 9.1.1 9.3.1 | 86-68420 | Commercial products data | 0 | 3 | 5 | Before fabrication or procurement | ||
M15 | Stop and drain valves | 9.1.1 9.3.1 | 86-68420 | Commercial products data | 0 | 3 | 5 | Before fabrication or procurement | ||
M16 | Curb stops | 9.1.1 9.3.1 | 86-68420 | Commercial products data | 0 | 3 | 5 | Before fabrication or procurement | ||
M17 | Traveling water screens | 9.1.1 9.4.1 | 86-68410 | (1) Commercial products data (2) Calculations (3) Drawings | 0 0 0 | 3 3 3 | 5 5 5 | Before fabrication or procurement | ||
M18 | Conveyors for traveling water screens | 9.1.1 9.4.2 | 86-68410 | (1) Commercial products data (2) Calculations (3) Drawings | 0 0 0 | 3 3 3 | 5 5 5 | Before fabrication or procurement | ||
M19 | Line meters | 9.1.1 9.4.3 | 86-68410 | Commercial products data | 0 | 3 | 5 | Before fabrication or procurement | ||
M20 | Vertical turbine pumping units | 9.1.1 9.5.1 | 86-68420 | (1) Commercial product data (2) Drawings (3) Test set up drawing | 0 | 3 | 5 | Before fabrication or procurement | ||
M21 | Vertical turbine pumping units | 9.1.1 9.5.1 | 86-68420 | Certified test data and reports | 0 | 3 | 5 | Before shipment | ||
M22 | Vertical turbine pumping units | 9.1.1 9.5.1 | 86-68420 | Installation manuals | 0 | 3 | 5 | Before shipment | ||
M23 | Vertical turbine pumping units | 9.1.1 9.5.1 | 86-68420 | Field alignment procedures | 0 | 3 | 5 | Before shipment | ||
M24 | Vertical turbine pumping units | 9.1.1 9.5.1 | 86-68420 | Millwright qualifications | 0 | 3 | 1 | Before shipment | ||
M25 | Vertical in-line screen spray pumping unit | 9.1.1 9.5.2 | 86-68420 | (1) Commercial product data (2) Drawings | 0 | 3 | 5 | Before fabrication or procurement | ||
M26 | Vertical in-line screen spray pumping unit | 9.1.1 9.5.2 | 86-68420 | Certified test data and reports | 0 | 3 | 5 | Before shipment | ||
M27 | Oil storage tank | 9.1.1 9.6.1 | 86-68420 | (1) Commercial products data (2) Drawings and data | 0 | 3 | 5 | Before fabrication or procurement | ||
M28 | Motor-operated slide gate | 9.1.1 9.7.1 | 86-68420 | (1) Commercial product data (2) Drawings and data (3) Motor Data | 0 | 3 | 5 | Before fabrication or procurement | ||
M29 | Ventilating systems (Approval Data) | 9.1.1 9.8.1 | 86-68410 | (1) Commercial products data (2) Power and control schematic and wiring diagrams. (3) Drawings and data showing operation of system. | 0 0 0 | 3 2 3 | 5 5 5 | Before fabrication or procurement | ||
M30 | Ventilating system (Procurement Data) | 9.1.1 9.8.1 | 86-68410 | (1) Dimensioned drawings of complete system. (2) Complete wiring diagrams of the system controls including dimensioned control panel layout and wiring designations and connections. (3)Bill of Materials. (4) Manufacturer’s data for testing and adjusting the equipment. | 0 0 0 0 | 3 3 3 3 | 5 5 5 5 | After RSN M29 submittals have been approved but before fabrication or procurement. | ||
M31 | Ventilating system (Final Data) | 9.1.1 9.8.1 | CE | (1) Test Reports (2) As Builts (3) Service Manuals | 0 0 0 | 3 3 3 | 1 0 0 | Prior to final system acceptance | ||
M32 | Steel manifold | 9.1.1 9.2.1 | 86-68420 | Final drawings | 0 | |